标题 |
超大断面黄土隧道CRD法开挖的三维有限元分析(50 卷) |
英文标题 |
Three-dimensional finite element analysis on excavation of loess tunnel with super-large cross section using CRD(Cross Diaphragm) method |
摘要 |
进口位于湿陷性砂质黄土中的凤凰岭隧道,开挖面积达170 m2,由于开挖难度巨大,采用了CRD法开挖技术。运用“PLAXIS 3D Tunnel”三维有限元程序,对CRD法的开挖过程进行了模拟,并考虑了降雨对隧道开挖的影响。计算得出了地表沉降和拱顶下沉,与现场实测值进行了对比分析。此 |
作者 |
新闻作者:薛富春,马建林,颜利平,赵永明,刘智毅,程琴辉 |